01 PIC present, Knowledgeable, Duties |
in |
|
|
|
0 |
01 0080-04-09-.02(1)(b) Demonstration of knowledge |
out |
Observed that PIC was not able to speak to thermometer calibration when asked to calibrate firm's thermometer. |
I was able to walk PIC through proper thermometer calibration using ice slurry and firm's thermometer was able to be calibrated. |
Priority Foundation (PF) |
1 |
24,25 Chemical hazards |
in |
|
|
|
0 |
24,25 25 Chemicals identified, stored, and used |
in |
|
|
|
0 |
24,25 0080-04-09-.07(2)(d)1 Sanitizers level over manufacture's suggested use |
out |
Observed that when PIC tested sanitizer using firm strips that it registered well above the manufacturer's suggested use level to the point that the test strip turned 'white' which is an indicator of too high sanitizer. |
PIC remade sanitizer inside sanitizer basin that tested adequately at 100 ppm using firm's and inspectors test strips. |
Priority (P) |
0 |
47,48,49 Plumbing |
in |
|
|
|
0 |
47,48,49 49 Sewage and waste water disposal |
in |
|
|
|
0 |
47,48,49 0080-04-09-.05(4)(c) Sewage and waste water properly disposed through public sewer or approved septic system; including condensate drainage |
out |
Observed wastewater back up into the 3 Compartment sink drains when running sink. Inspector advised PIC to clean their grease traps regularly to insure proper wastewater drainage. |
|
Priority (P) |
0 |