| 01 PIC present, Knowledgeable, Duties |
in |
|
|
|
0 |
| 01 0080-04-09-.02(1)(c) Person in charge - Duties |
out |
At time of inspection employee did not know how to properly sanitize food contact equipment. Employee called the Manager (PIC) who was unaware how to create a sanitizer sink, stating that another employee that was fired last week did the cleaning. PIC was unaware that hot water is needed at kitchen, prep area, and bathroom hand sinks. PIC did not know how strong sanitizer solution needs to be. |
|
Priority Foundation (PF) |
0 |
| 14 Food contact surfaces; clean and sanitized |
in |
|
|
|
0 |
| 14 0080-04-09-.04(6)(a) Food contact surfaces shall be visually clean. |
out |
Kitchen/Prep Area- tongs and pizza server were not used today but had old food residue on portions of tongs and pizza server that touch food. |
PIC placed tongs and pizza server in ware wash area. |
Priority Foundation (PF) |
0 |
| 24,25 Chemical hazards |
in |
|
|
|
0 |
| 24,25 25 Chemicals identified, stored, and used |
in |
|
|
|
0 |
| 24,25 0080-04-09-.07(2)(d)1 Sanitizers level over manufacture's suggested use |
out |
PIC was asked to create a sanitizer sink so it could be tested. Inspector tested the chlorine sanitizer sink at more then 200PPM and 107 degrees. |
|
Priority (P) |
0 |
| 33 Thermometers provided and accurate |
in |
|
|
|
0 |
| 33 0080-04-09-.04(3)(b)2 Probe thermometer shall be readily accessible to check food temperatures |
out |
At time of inspection employee could not find a probe thermometer. |
|
Priority Foundation (PF) |
1 |
| 44,45 Utensils and equipment |
in |
|
|
|
0 |
| 44,45 45 Warewashing facilities installed, maintained, and used; test strips |
in |
|
|
|
0 |
| 44,45 0080-04-09-.04(3)(b)4 Test Kits to measure concentration of sanitizing solutions. |
out |
At time of inspection PIC could not locate any test strips. |
|
Priority Foundation (PF) |
2 |
| 47,48,49 Plumbing |
in |
|
|
|
0 |
| 47,48,49 47 Hot and cold water available |
in |
|
|
|
0 |
| 47,48,49 0080-04-09-.05(1)(c) Hot and cold running water at sinks |
out |
Kitchen/Prep Hand sink- PIC states hand sink has its own separate water line from the 3 bay sink. At time of inspection hand sink was under 70 degrees when checked after several minutes. Kitchen closure was issued until firm has hot water at kitchen hand sink. ////#2-Male/Female restroom- Per PIC male and female restroom do not have hot water. |
|
Priority Foundation (PF) |
0 |